Advertisement

Water main installation project to begin on Gardenia Drive in Cheyenne

Water shut offs will be coordinated, but unplanned emergency shut offs may occur.
Water shut offs will be coordinated, but unplanned emergency shut offs may occur.(Cheyenne Board of Public Utilities)
Published: May. 11, 2022 at 5:11 PM CDT
Email This Link
Share on Pinterest
Share on LinkedIn

CHEYENNE, Wyo. (PRESS RELEASE) - The City of Cheyenne Board of Public Utilities (BOPU) anticipates construction activities to begin on a water main installation project along Gardenia Drive the week of May 16, 2022.

This portion of the project is expected to last three to four weeks, depending on weather and material availability. Please see below map for construction location.

The BOPU will work diligently to keep businesses accessible, however, vehicles should not be parked in the Right-of-Way within the work zone between 7:00 AM and 6:00 PM, Monday through Friday, and Saturdays on occasion. This area will be clearly marked.

Water shut offs will be coordinated, but unfortunately unplanned emergency shut offs may occur. This project will advance water service reliability for the area and is part of the BOPU’s initiative to accelerate the renewal of water infrastructure that has reached the end of its useful life.

Construction location of the project
Construction location of the project(Cheyenne Board of Public Utilities)

Copyright 2022 Wyoming News Now. All rights reserved.